What is the most efficient method for importing a large batch of XER files into a P6 database?
AI Answer
Most Efficient Methods for Batch Importing XER Files into a P6 Database:
When dealing with a large number of XER files, manual import through the P6 interface is impractical. Below are the recommended approaches, ranked by efficiency and reliability.
1. P6 Integration API (Best for EPPM environments):
- The
P6 Integration API(REST or Java-based SDK) is the most robust solution for bulk imports. - Write a script that iterates through XER files and calls the API sequentially or in parallel.
- Supports logging, error handling, and scheduling — far superior to manual UI imports.
- Suitable for enterprise environments running
P6 EPPM. P6 Professionaldoes not natively support command-line XER import, but you can automate theTools > Importworkflow using UI automation tools such as AutoIt, PowerShell with SendKeys, or similar.- Less elegant but effective for straightforward batch jobs.
- Prone to breaking if P6 UI changes — always test on a small batch first.
- XER files are plain-text, tab-delimited files with a well-known structure.
- Open-source Python libraries such as
xerparsercan parse XER files and allow programmatic insertion into the P6 database (PostgreSQL or MSSQL). - Warning: Direct database manipulation bypasses P6 business logic, risks data integrity issues, and is unsupported by Oracle. Only use in controlled environments with a full database backup.
- Requires deep knowledge of the P6 database schema.
- Some commercial scheduling tools and consultants offer bulk XER migration utilities.
- Evaluate carefully — ensure compatibility with your specific P6 version and database type.
- Always take a full database backup before any bulk import operation.
- Import in smaller batches (e.g., 50 files at a time) to simplify troubleshooting if errors occur.
- Validate a sample of imported projects post-import to confirm data integrity (activities, relationships, resources, calendars).
- If projects share global data (calendars, resources, codes), resolve conflicts and set import settings consistently before batch processing.
- Use
P6 Professionalimport settings to control how conflicts are handled: Update existing vs Create new for projects, resources, and calendars.
2. Automated Script with P6 Professional UI (Practical alternative):
3. Python XER Parser + Direct Database Insert (Advanced users only):
4. Third-Party Migration Tools:
Practical Recommendations:
Summary Table:
Method | Speed | Complexity | Risk
P6 Integration API | High | Medium | Low
UI Automation Script | Medium | Low-Med | Low-Med
Python + DB Insert | High | High | High
Third-Party Tools | Varies | Low | Medium
Generated by AI — reviewed by our team
Related Questions
Can you compare P6 Professional (the desktop version) with Oracle Primavera Cloud in terms of the Scheduling Engine? Also provide a comparison from an Admin and update perspective.
I defined a Level of Effort (LoE) activity in P6 spanning the entire project duration and assigned a cost resource to it that should be expensed according to project progress. However, even though the activity has an SS relationship and has started, the LoE activity shows zero progress and zero actual units. How can I make it automatically pick up progress?
In P6, I define a User Defined Field and create a Global Change to set that field equal to BL3 Finish minus Finish. When I apply it, it only runs on activities. Is there a way to make it roll up to the WBS Summary levels above, like in MS Project?